1. Project Management and Engineering Services Unit in Kozloduy NPP for fulfillment of different tasks for the decommissioning of Units 1 and 2 (subcontractor of BNFL/EDF).

2. Elaboration of a project for complete radiation surveillance of Kozloduy NPP Units 1&2 – subcontractor of EWN.

3. Independent review and safety assessment of Kozloduy Unit 5 in case of beyond design failure of the control rod drives.

4. Rest life time evaluation for systems and equipment for spent fuel storage and for the technological systems in the spent fuel storage of Kozloduy NPP.

5. Design of thermal insulation of equipment and pipelines in Unit 1 of Maritza Iztok 2 thermal power plant.

6. Detailed design of the modernization of the destructor of the incinerator plant for burning of hazardous wastes from hospitals.

7. “Investigation of the possible pathways and technical means, design and installation of alternative FW to SGs in case of SBO for units 5 and 6 at KNPP.

8. Development of a program for investigation, analysis and evaluation of the mechanical characteristics of pipelines group “B” for unit 6 at KNPP after 100,000 years of operation (subcontractor to ATP).